About the project

Project acceleration program for leading truck manufacturer to increase eliminate constraints and establish flow, meeting critical delivery dates of armored trucks. After six months, assembly run 25% faster, first-pass quality increased by 60%, a major schedule delay was caught up, and all 83 vehicles were shipped on time.

  • Industry: automotive
  • Scope: assembly, engineering, key suppliers
  • Locations: France and Germany
  • Duration: 6 months
  • Support: 165 days on-site
  • Speed: 25% reduced cycle time
  • Quality: +60% first-pass yield
  • Delivery: 100% on time (caught up major delay)